Year wise processing of Single Village Schemes (SVS) Detailed Project Reports (DPRs) at GoUK, SWSM & DWSM Level
Rs. In Lakhs
Financial Year |
Sanctioned | |||||||
GoUK | SWSM | DWSM | Total | |||||
No | Cost | No | Cost | No | Cost | No | Cost | |
2009-10 | 0 | 0.00 | 3 | 217.28 | 2267 | 37223.00 | 2270 | 37440.28 |
2010-11 | 0 | 0.00 | 2 | 195.18 | 408 | 4299.28 | 410 | 4494.46 |
2011-12 | 6 | 804.01 | 32 | 2449.65 | 497 | 8388.00 | 535 | 11641.66 |
2012-13 | 14 | 1895.75 | 5 | 302.07 | 0 | 0.00 | 19 | 2197.82 |
Total | 20 | 2699.76 | 42 | 3164.18 | 3172 | 49910.28 | 3234 | 55774.22 |
Year wise processing of Multi Village Schemes (MVS) Detailed Project Reports at GoUK, SWSM & DWSM Level
Rs. In Lakhs
Financial Year |
Sanctioned | |||||||
GoUK | SWSM | DWSM | Total | |||||
No | Cost | No | Cost | No | Cost | No | Cost | |
2010-11 | 11 | 2728.78 | 10 | 821.54 | 8 | 285.72 | 29 | 3836.04 |
2012-13 | 10 | 2532.23 | 0 | 0.00 | 0 | 0 | 10 | 2532.23 |
2013-14 | 0 | 0.00 | 1 | 46.87 | 0 | 0 | 1 | 46.87 |
Total | 21 | 5261.01 | 11 | 868.41 | 8 | 285.72 | 40 | 6415.14 |